Over $4B being spent to develop first phase of Enmore/Foulis industrial & commercial zone

Minister of Housing and Water Collin Croal inspect ongoing works (Photo: CH&PA/February 22, 2024)

Of the six lots, Croal noted that two lots are more than 90% completed; the overall project is about 60% complete.

“In the first phase, we are currently developing over 660 acres of land on this site now and we’re spending about over $4.58 billion in the first-phase infrastructure,” Croal was quoted as saying in the press release.

The industrial and commercial hub is set to feature three main access roads to accommodate large trucks.

The works, Croal said have significantly transformed the area, which was once dominated by sugar canes.

Works are progressing on the Enmore/Foulis Industrial and Commercial zone on the East Coast of Demerara (Photo: CH&PA/February 22, 2024)

“Minister Croal outlined the zoning plan for the area, specifying sections dedicated to heavy industrial, light industrial, and commercial activities,” the release noted.

In the Enmore residential housing scheme, located north of the commercial area, the release said Minister Croal noted that several allottees have gained access to their land for home construction, paralleling the progress of infrastructure works.

Ahead to the 2024 housing programme, Croal anticipates that contracts will be awarded soon for the development of numerous housing schemes.