Power ship arrives at Everton; connection to begin on Sunday

The 36-megawatt power ship, which will provide extra power to the national grid sailed to Everton, Berbice on Saturday and works are expected to commence on Sunday to connect it.

The power ship arrived in Guyana on Wednesday.

Officials from Karpowership International from Turkey, through which it is being rented by the Guyana Power and Light (GPL), were on the ground on Saturday for the ship’s arrival there.

The power ship arrived in Guyana on Wednesday (Photo: News Room/May 04, 2024)

At the site, preparatory work, including the driving of piles and the installation of transmission lines,  are ongoing.

Speaking to the News Room at the site, GPL’s Berbice Zone Manager Ravindra Jagnanan said the power ship will take up its final position on Sunday after which works will begin to connect it to the national grid.

“The power ship is here.

“Once the ship is docked, the final stage would be to connect the ship to the network. When that is done we have a little bit of maintenance more to do on our transmission line and then we could inject power into the power grid,” Jagnanan explained.

The connection process, Jagnanan said, should take about two days.

At the site, preparatory work, including the driving of piles and the installation of transmission lines,  are ongoing (Photo: News Room/May 04, 2024)

However, he pointed out that if the rain persists, it can hinder the process.

The power ship arrived with about 100 meters of cable. This, Jagnanan said, will be used to make the necessary connection to GPL’s transmission line structure.

“Our network will be able to take off and utilise all of the power from the ship,” he said.

Prior to the arrival of the vessel, Jagnanan further explained that the team has been working “assiduously” to get all the preparatory works completed.

“We would have started with the pile driving process to secure and moor the vessel because the stability is paramount to the operation,” he noted.

Another important aspect of the works, Jagnanan, said is to ensure that there is “enough” lighting in the compound at Everton to ensure “proper” secutiry of the power ship and the crew.

“We have been really working to get things done. The weather did pose some challenges butthanks to the teams who are fully committed to execute their mandate,” he said.

At the site, preparatory work, including the driving of piles and the installation of transmission lines,  are ongoing (Photo: News Room/May 04, 2024)

GPL has already paid a mobilisation fee of US$1 million to rent the power ship and it will pay 6.62 cents per kilowatt hour as a monthly charter fee plus 0.98 cents per kilowatt hour on maintenance, based on electricity generated.

The deal to rent the powership was signed on April 13 with Urbacon Concessions Investments, W.L.L (UCI) to rent the power ship for two years.

Karpowership, Executive Director of Operations, Osman Yalman said the company hopes that the initiative will be beneficial the country.

“We just bring one of our power ship which we are planning to give the grid 36 megawatts…We hope this will be beneficial for the country.

“All the operations is ongoing. Everyone is working very hard…We are doing something…which is very, very short,” Yalman told the News Room.

The power ship consists of two entrances, which can provide 18.5 megawatts each.